Analysis of the construction process of cable-stayed bridges built on temporary supports

Author
Lozano-Galant, J.A.; Payá, I.; Xu, D.; Turmo, J.
Type of activity
Journal article
Journal
Engineering structures
Date of publication
2012-06
Volume
40
First page
95
Last page
106
DOI
https://doi.org/10.1016/j.engstruct.2012.02.005 Open in new window
URL
https://www.sciencedirect.com/science/article/pii/S0141029612000636 Open in new window
Abstract
The temporary supports erection method is a fast and economical way of building cable-stayed bridges. In this method the bridge deck is first erected on a set of temporary and permanent supports and then, the stays are successively placed and tensioned according to a predefined tensioning sequence. A proper definition and analysis of this sequence is very complex as the structure is highly statically indeterminate, exhibits a non linear behavior and has a changing static scheme. Despite its imp...
Keywords
Backward modeling, Cable-stayed bridges, Construction process, Temporary supports erection method