Preload improvement and monitoring in a newly reclaimed area

Author
Tarragó Munté, Daniel; Gens, A.; Alonso, E.; Deu, A.; Griell, R.
Type of activity
Presentation of work at congresses
Name of edition
International Conference on Ground Improvement and Ground Control: Transport Infrastructure Development and Natural Hazards Mitigation
Date of publication
2012
Presentation's date
2012-11
Book of congress proceedings
International Conference on Ground Improvement and Ground Control: transport infraestructure development and natural hazards mitigation, ICGI 2012: Wollongong, Australia: 30 October-2 November, 2012: proceedings
First page
389
Last page
394
Publisher
Research Publishing
DOI
https://doi.org/10.3850/978-981-07-3559-3_01-0108 Open in new window
Repository
http://hdl.handle.net/2117/18310 Open in new window
http://rpsonline.com.sg/proceedings/9789810735777/html/01-0108.xml Open in new window
Abstract
The paper describes the preload improvement of a newly reclaimed area that is part of the current development of the Barcelona Port. The area will provide the required surface of a new container terminal with a berth length of 1,600 m. The total surface area is 750,000 m2. The improvement affects both the hydraulic fill placed for the reclamation as well as the underlying soft natural ground. Improvement was required for both reducing subsequent settlements and providing an adequate level of sta...
Citation
Tarrago, D. [et al.]. Preload improvement and monitoring in a newly reclaimed area. A: International Conference on Ground Improvement and Ground Control. "International Conference on Ground Improvement and Ground Control: transport infraestructure development and natural hazards mitigation, ICGI 2012: Wollongong, Australia: 30 October-2 November, 2012: proceedings". Wollongong: Research Publishing, 2012, p. 389-394.