Innovative solutions for intersection of TBM tunnel and station in Riyadh Line 5 metro

Autor
Ramos, G.; García-fontanet, A.; Torralba, V.; Ainchil, J.
Tipus d'activitat
Article en revista
Revista
Tunnelling and underground space technology
Data de publicació
2018-10
Volum
80
Pàgina inicial
26
Pàgina final
37
DOI
https://doi.org/10.1016/j.tust.2018.05.024 Obrir en finestra nova
Repositori
http://hdl.handle.net/2117/118485 Obrir en finestra nova
https://www.researchgate.net/publication/325845995_Innovative_solutions_for_intersection_of_TBM_tunnel_and_station_in_Riyadh_Line_5_metro Obrir en finestra nova
URL
https://www.sciencedirect.com/science/article/pii/S088677981730295X Obrir en finestra nova
Resum
One of the main problems when constructing a metro line using a tunnel boring machine (TBM) is the coordination of the construction of the tunnel with the excavation of the stations that it will intersect, being possible to reach the stations before their complete excavation. This paper presents a solution to this problem, one which has been implemented in the Riyadh Metro L5. This solution allows the construction of the tunnel and the later excavation of the station, while maintaining the opera...
Citació
Ramos, G., García-fontanet, A., Torralba, V., Ainchil, J. Innovative solutions for intersection of TBM tunnel and station in Riyadh Line 5 metro. "Tunnelling and underground space technology", Octubre 2018, vol. 80, p. 26-37.
Paraules clau
Precast lining, Station construction, TBM tunnel